All Projects — 37 issues

Notice

3
N002Stormwater Pond Relocation
$450KR2B
N005Noise Wall Foundation
$120KR2B
N012Marine Habitat Mitigation
$280KPBB

Protest

6
P017NFP Creek West Wetland
TBDDBMar 20BYD
P018Juanita Creek West Wetland
$14KDBMar 20BYD
P019Juanita Creek Lateral Migration
$5.5MDBMar 24BYD
P008Retaining Wall Redesign
$1.75MR2B
P009Signal Conduit Relocation
$340KR2B
P010Barge Access Restriction
$3.4MPBB

Determination

4
P005Utility Conflict — Gas Main
$2.3MR2B
P007Median Barrier Redesign
$870KR2B
P011Pontoon Ballast Redesign
$1.5MPBB

Claim / Hearing

4
P001Seismic Retrofit Scope
$8.9MPBB
P001Differing Site Conditions
$6.2MR2B
P003Post-Tension Anchor Delay
$2.1MPBB
P007HB 2081 B&O Tax
$27KDBBYD

Resolved / Closed

5
P015Contaminated Soil (BNSF)
$197KBYD
P002Temporary Navigation Channel
$175KPBB
P004Temporary Erosion Control
$95KR2B
P005Juanita Creek Design
BYD
P008Juanita Creek Angular Rock
BYD
I-405/SR 522 Brickyard Contract 9727 19 issues

Determination

0
No issues

All Issues

19
ID Title Stage Amount BIC Next Action Deadline
P001Vault NW12Dispute$2.1MWSDOTDispute responseMar 20
P002BRT Station DesignDispute$1.9MTBDDRB referral
P003Lateral MigrationDispute$7.8MTBDDRB referral
P004SR 522 Comfort Hub SepticDispute$616KTBDDRB referral
P005Juanita Creek DesignResolved
P006DSC 006Dispute$25.4MTBDDRB referral
P007HB 2081 B&O TaxClaim$27KDBCertified Claim
P008Juanita Creek Angular RockClosed
P009SR522 Transit Hub LightingDispute$332KTBDDRB referral
P010WaterproofingDispute$1.2MTBDDRB referral
P011SR522 Transit Hub PowerDispute$1.1MTBDDRB referral
P012CCTV PoleDispute$105KTBDDRB referral
P013KCM Power VaultDisputeTBDWSDOTDispute responseMar 30
P014Bridge 405/103E ATC-1Supplemental$1.4MWSDOTDeterminationMar 27
P015Contaminated Soil (BNSF)Resolved$197K
P016Bridge 405/70N-W DeckSupplementalTBDWSDOTDeterminationApr 03
P017NFP Creek West WetlandProtestTBDDBSupplement dueMar 20
P018Juanita Creek West WetlandProtest$14KDBSupplement dueMar 20
P019Juanita Creek Lateral MigrationProtest$5.5MDBSupplement dueMar 24
I-405 Renton to Bellevue Contract 9840 Example 10 issues

Notice

2
N002Stormwater Pond Relocation
$450K
N005Noise Wall Foundation
$120K

Protest

2
P008Retaining Wall Redesign
$1.75M
P009Signal Conduit Relocation
$340K

Determination

2
P005Utility Conflict — Gas Main
$2.3M
P007Median Barrier Redesign
$870K

Dispute

2
P002Temporary Shoring Scope
$4.1M
P003Drainage Outfall Redesign
$680K

Hearing

1
P001Differing Site Conditions
$6.2M

Closed

1
P004Temporary Erosion Control
$95K
SR 520 Portage Bay Bridge Contract 9215 Example 8 issues

Notice

1
N012Marine Habitat Mitigation
$280K

Protest

1
P010Barge Access Restriction
$3.4M

Determination

1
P011Pontoon Ballast Redesign
$1.5M

Dispute

2
P006Concrete Mix Specification
$920K
P008Column Pier Foundation
$5.7M

Hearing

2
P001Seismic Retrofit Scope
$8.9M
P003Post-Tension Anchor Delay
$2.1M

Closed

1
P002Temporary Navigation Channel
$175K