INTERNAL / PRIVILEGED — DRAFT

Protest 006: DSC 006 Clay Layer ESU 2C — PCO 123

Contract 9727 — I-405, Brickyard to SR 527 — Change Order not to exceed $35,000,000 — 129 calendar days — Walls 23.80R, 23.72R, 23.73R, 23.74R and Abutment 10