Protest Timeline

Protest 009 · SR 522 Transit Hub Lighting (Issue ISS-256) · Dispute — DRB Preparation

DatePartyLetterEvent
2025-10-17SkanskaLTR 255Requests OIC for SR 522 Transit Hub roadway lighting requirements
2025-11-17WSDOTSL 9727-199Denies OIC; proposed fixture acceptable but mounting height must comply with ST Design Criteria Manual; approves increase to 24ft
2025-12-01SkanskaLTR 285Notice of Protest 009; asserts WSDOT interpretation unreasonable; requests 60 days for supplement
2025-12-09WSDOTSL 9727-214Acknowledges protest; denies time extension; supplement due December 15
2025-12-23SkanskaLTR 306Supplement (8 days late); design costs $332,468 (AECOM); construction TBD; schedule at risk for Milestone C
2026-01-07WSDOTSL 9727-234Determination of no merit
2026-01-22SkanskaLTR 325Dispute Notification per Section 1-04.5(1); TIA required but scope pending
2026-01-29WSDOTSL 9727-253Acknowledges dispute; awaits Dispute Referral per Section 1-04.5(1).18

Lifecycle: Notice → Protest → Determination (No Merit) → Dispute Filed → Awaiting DRB Referral

Open: Dispute Referral not yet received as of March 2026. TIA pending. Construction costs TBD.