Protest 010 — BRT Station Waterproofing IED

Protest Timeline · ISS-010 · Dispute Stage · As of March 2026

Overview

WSDOT issued SL 9727-209 (December 3, 2025) as an Interpretive Engineering Decision (IED) under GP 1-03.5, requiring below-grade sheet-applied membrane waterproofing and watertight elevator pits at Brickyard West, East, and Canyon Park BRT stations. Skanska protested (LTR 287, December 5), supplemented (LTR 301, December 19), and filed a second supplement (LTR 310, December 31). WSDOT denied all claims (SL 9727-239, January 9, 2026). Skanska filed a Dispute Notification (LTR 331, January 23, 2026) and is proceeding with work while disputing.

Timeline

Date Party Letter Description
2025-12-03 WSDOT SL 9727-209 Interpretive Engineering Decision: below-grade sheet-applied membrane waterproofing and watertight elevator pits required at Brickyard West, East, and Canyon Park BRT stations
2025-12-05 Skanska LTR 287 Notice of Protest 010 against waterproofing and elevator pit requirements. Triggering letter.
2025-12-19 WSDOT SL 9727-221 Acknowledges Notice of Protest 010. Confirms Written Determination forthcoming.
2025-12-19 Skanska LTR 301 Supplemental information. Claims inconsistency in WSDOT’s position. Proposes accepting Work as constructed (Hycrete-only approach).
2025-12-31 Skanska LTR 310 Responds to SL 9727-221. Asserts that the spec as written would void the Hycrete warranty if membranes applied to existing substrate. Suggests DBIC to eliminate membrane requirement.
2026-01-09 WSDOT SL 9727-239 Denies all claims. Suggests DBIC path for Sound Transit written approval. Clarification: if membrane applied to vertical surfaces, pit slab at Brickyard West need not be replaced.
2026-01-23 Skanska LTR 331 Dispute Notification per RFP Section 1-04.5(1). Will proceed with work as directed while continuing to dispute. Dispute stage begins.

Procedural Status

Step Status Notes
Notice of Protest Complete LTR 287 (Dec 5, 2025) — 2 days after SL 9727-209. Timely.
WSDOT Acknowledgment Complete SL 9727-221 (Dec 19, 2025)
Supplemental Submissions Complete LTR 301 (Dec 19) and LTR 310 (Dec 31)
WSDOT Written Determination Complete SL 9727-239 (Jan 9, 2026) — protest denied
Dispute Notification Complete LTR 331 (Jan 23, 2026) — 14 days from SL 239. Timely.
DRB Referral Pending Awaiting written Dispute Referral from Skanska per Section 1-04.5(1).18

Key Contract Provisions

Section Purpose
GP 1-03.5IED authority — WSDOT may issue its own IEDs; IEDs do not create cost/time entitlement
S07 07 10 00Membrane waterproofing requirements at below-grade elements
S07 07 13 53Elastomeric sheet membrane waterproofing specification
S07 03 15 13 Part 2.01.CButyl-strip waterstops in Hycrete concrete require exterior membranes
S07 14 24 00Hydraulic elevator pit must be watertight/sealed before installation
DCM 25.4.1.JElevator pits must prevent groundwater entry and fluid release
GP 1-03.2Order of Precedence — Technical Requirements control over building code
GP 1-03.7Reviews/approvals do not constitute waivers
GP 1-04.4(5)(b)Design review corrections are not eligible for change orders