Protest 011 — Revised PSE Power Routing to Transit Hub

Protest Timeline · ISS-230 · Dispute Stage · As of March 2026

Overview

Skanska notified WSDOT in November 2025 of design impacts related to revised PSE power routing to the SR-522 Transit Hub (LTR 273). WSDOT found no merit (SL 9727-203). Skanska protested (LTR 289). WSDOT denied the extension request (SL 9727-211). Skanska submitted a supplemental claim of $1,112,424 (LTR 300). WSDOT again found no merit (SL 9727-238). Skanska filed a Dispute Notification (LTR 328). WSDOT acknowledged and requested a written Dispute Referral (SL 9727-251). Awaiting Dispute Referral.

Timeline

Date Party Letter Description
2025-11-07 Skanska LTR 273 Notifies WSDOT of design impacts related to temporary power at SR-522 Transit Hub. AECOM initial estimate: $340,362.
2025-11-21 WSDOT SL 9727-203 No merit for extra cost on temporary signal power design. First written determination.
2025-12-05 Skanska LTR 289 Notice of Protest 011. Requests 60-day extension to submit supplemental information.
2025-12-08 WSDOT SL 9727-211 Denies 60-day extension. Sets supplemental deadline: December 19, 2025.
2025-12-19 Skanska LTR 300 Supplemental information. Claim increased to $1,112,423.95 (Skanska $598,750 + AECOM $513,674). States no additional Contract Days if RFC design complete by 2/20/26.
2026-01-09 WSDOT SL 9727-238 Responds to supplemental. No merit determination on cost claim.
2026-01-23 Skanska LTR 328 Dispute Notification per Section 1-04.5(1). Dispute stage begins.
2026-01-26 WSDOT SL 9727-251 Acknowledges DRB request. Requests written Dispute Referral per Section 1-04.5(1).18.

Procedural Status

Step Status Notes
Initial Notice (LTR 273) Complete Nov 7, 2025 — design impacts notification
WSDOT First Determination Complete SL 9727-203 (Nov 21, 2025) — no merit
Notice of Protest Complete LTR 289 (Dec 5, 2025)
Extension Denied Complete SL 9727-211 (Dec 8, 2025)
Supplemental Submitted Complete LTR 300 (Dec 19, 2025)
WSDOT Second Determination Complete SL 9727-238 (Jan 9, 2026) — no merit
Dispute Notification Complete LTR 328 (Jan 23, 2026)
WSDOT Acknowledgment Complete SL 9727-251 (Jan 26, 2026)
Written Dispute Referral Pending Awaiting from Skanska per Section 1-04.5(1).18
DRB Preparation In Progress Position paper development underway

Claim Summary

Component Amount
Skanska direct costs$598,750.00
AECOM redesign costs$513,673.95
Total Claimed$1,112,423.95
Schedule Extension Claimed0 days (conditional on RFC by 2/20/26)

WSDOT Position

No merit. The Design-Builder is responsible for the PSE power routing design to the Transit Hub under the contract. WSDOT determined no extra cost is warranted for temporary signal power design. No Change Order was issued. The DB’s cost claim reflects design effort to meet its own contractual obligations, not costs attributable to a WSDOT-directed change.

DRB position paper is in development. Key issues include: (1) whether the PSE routing change was within the DB’s design scope, (2) whether any WSDOT action constituted an OIC under GP 1-04.4(1), and (3) the basis for the 3× increase in AECOM’s cost estimate from initial ($340K) to supplemental ($514K).