Notice
Protest
Determination
Dispute
Hearing

1. Executive Summary

Decision Requested

Evaluate Skanska LTR 378 (March 16, 2026) and respond to the AECOM Notice of Dispute and three proposed resolution paths for the KCM power vault relocation claim.

  • Recommendation: Deny — protest determination stands; evaluate resolution proposals on merits
  • Cost Exposure: Not quantified; Force Account tracking in progress per SL 9727-188
  • Risk Level: Moderate — unresolved legal authorization question for KCM ROW occupancy

Core Question

Does the KCM power vault qualify as a Major Underground Utility entitling Skanska to a WSDOT-Initiated Change, or is vault relocation within the Design-Builder’s base scope as a property improvement or appurtenance on the Right of Way?

Skanska requested a WSDOT-Initiated Change for relocation of a King County Metro (KCM) power vault encountered during construction on the I-405/Brickyard to SR 527 project. WSDOT determined the vault does not meet the definition of a Major Underground Utility under GP 1-07.17(9) (SL 9727-217, December 11, 2025) and reaffirmed that position on reconsideration (SL 9727-235, January 8, 2026). Skanska filed a formal protest on January 22, 2026 (LTR 327) and supplemented it on February 9, 2026 (LTR 345).

WSDOT denied the protest on March 2, 2026 (SL 9727-285), citing GP 1-07.17(9).4 Item 3 (no change order for inaccuracies in non-Major Utility information), GP 1-07.16(1) (DB must protect improvements legally on the ROW), and RFP Section 2.16.3.5.6 (existing vaults must meet heavy-duty standards or be relocated). Skanska responded on March 16, 2026 (LTR 378) — the last day of the 14-day dispute window — with two components: (1) a substantive rebuttal of SL-285 arguing that complete omission differs from inaccuracy and challenging the legal authorization for KCM’s ROW occupancy, and (2) an attached AECOM Notice of Dispute dated March 13, 2026, formally invoking Section 1-04.5(1) and reserving DRB referral rights.

WSDOT response to LTR 378 is due March 30, 2026. The dispute is assigned JS. Three resolution paths proposed by Skanska require evaluation: Force Account conversion under Section 1-09.6, WSDOT-Initiated Change under Section 1-04.4(1), and Cost Responsibility Determination under Section 1-07.17(10).

Issue ID
SKA-0247 / PCN-00142
Amount Claimed
Not quantified
Time Impact
TBD
Status
Deny

2. Skanska Assertions and WSDOT Position

A Vault qualifies as Major Underground Utility Strong

Skanska Assertion

The KCM power vault is a Major Underground Utility under GP 1-07.17(9) and should be processed as a WSDOT-Initiated Change under Section 1-04.4(1).

WSDOT Position

WSDOT determined (SL 9727-217; SL 9727-235) the vault does not meet the Major Underground Utility definition. WSDOT’s final determination (SL 9727-285) further cited GP 1-07.17(9).4 Item 3, which bars a change order for “inaccuracies in Utility Information” for non-Major Utilities, and RFP Section 2.16.3.5.6, which requires existing vaults to meet Heavy Duty standards or be relocated — placing relocation within DB scope.

GP 1-07.17(9) · GP 1-07.17(9).4 Item 3 · RFP 2.16.3.5.6
B Omission differs from inaccuracy — GP 1-07.17(9).4 does not apply Moderate

Skanska Assertion (LTR 378)

GP 1-07.17(9).4 Item 3 bars change orders for “inaccuracies” in utility information. The KCM vault was not listed in Appendix U2 (Existing Utility Listing), U3 (Utility Owner Contact List), or N1 as-builts at all. A complete omission is fundamentally different from an inaccurate depiction, and the provision should not apply.

WSDOT Position

WSDOT’s SL-285 did not directly address the omission/inaccuracy distinction. This argument requires a substantive response in the upcoming LTR 378 reply. Skanska’s reading has textual support if the provision is construed narrowly. WSDOT’s strongest counterargument is that GP 1-07.16(1) independently covers this situation by placing responsibility on the DB to protect all improvements legally on the ROW regardless of whether they appear in contract documents.

GP 1-07.17(9).4 Item 3 · GP 1-07.16(1)
C KCM has no documented legal authorization for ROW occupancy Available

Skanska Assertion (LTR 378)

GP 1-07.16(1) requires the DB to protect improvements “legally on the Right of Way.” WSDOT has not produced any permit, franchise agreement, easement, or other authorization for KCM to occupy the Limited Access ROW. An undisclosed, unauthorized facility cannot be an improvement the DB was obligated to protect under GP 1-07.16(1).

WSDOT Position

Open item: WSDOT must verify whether documentation of KCM’s legal authorization for ROW occupancy exists. If authorization cannot be documented, WSDOT’s reliance on GP 1-07.16(1) is weakened. This is identified as a medium-priority open item requiring follow-up before the March 30 response deadline.

GP 1-07.16(1)
D RFP 2.16.3.5.6 addresses WSDOT electrical infrastructure, not third-party facilities Available

Skanska Assertion (LTR 378)

RFP Section 2.16.3.5.6 addresses WSDOT electrical infrastructure identified in the Contract Documents, not undisclosed third-party (KCM) facilities. The section cannot be invoked to place relocation responsibility on the DB for a utility that WSDOT failed to disclose.

WSDOT Position

Requires evaluation of RFP 2.16.3.5.6 text and context. If the section is limited to identified WSDOT infrastructure, Skanska’s argument has merit. WSDOT introduced this provision as a new basis in SL-285 (not raised in earlier letters), which means it has not yet been fully tested in the correspondence record.

RFP 2.16.3.5.6

3. Risk

Strengths

  • WSDOT’s classification determination has been reaffirmed twice (SL 9727-217, SL 9727-235) and upheld through the formal protest process (SL 9727-285).
  • GP 1-07.17(9).4 Item 3 provides a textual basis for barring a change order even if the vault information was inaccurate (WSDOT’s broader reading of “inaccuracies”).
  • GP 1-07.16(1) places a general duty on the DB to protect improvements on the ROW, which could independently support denial regardless of utility classification.

Potential Weaknesses

  • The omission/inaccuracy distinction raised in LTR 378 has textual support and was not addressed in SL-285 — creates a gap in the record that DRB may scrutinize.
  • If WSDOT cannot document KCM’s legal authorization for ROW occupancy, the GP 1-07.16(1) defense collapses on its own terms.
  • WSDOT’s classification shifted across letters (Major Underground Utility vs. Service Line vs. “property improvement/appurtenance”), which Skanska correctly notes as inconsistent — the term “property improvement/appurtenance” does not appear in the Contract.
  • KCM’s refusal to provide direction and subsequent radio silence after the February 18 meeting leaves the path forward unclear and reflects poorly in the correspondence record.

Defense Layering

LayerDefenseUse In
1. GP 1-07.17(9).4 Item 3 — no CO for non-Major Utility information issues (WSDOT’s broader reading: “inaccuracies” encompasses omissions) Determination / DRB
2. GP 1-07.16(1) — DB duty to protect improvements legally on ROW (contingent on KCM authorization documentation) Determination / DRB
3. RFP 2.16.3.5.6 — vault must meet Heavy Duty standards or be relocated (scope argument) Determination
4. Section 1-07.17(10) cost responsibility determination — Skanska’s own proposed resolution path; evaluating this could resolve without DRB Resolution Negotiation

Fallback Position

If a DRB determines the vault omission distinguishes this from GP 1-07.17(9).4, WSDOT may need to evaluate the Force Account conversion proposal (Skanska’s Resolution Path 1) or the Section 1-07.17(10) cost responsibility determination (Resolution Path 3) as settlement alternatives to avoid full DRB hearing on an unquantified claim.

4. Chronology

WSDOT
Skanska
Milestone
Oct 2025 – Mar 2026 Full timeline →
Date Event
2025-10-17 Skanska LTR 257 — Requests WSDOT-Initiated Change for KCM power vault relocation
2025-10-30 WSDOT SL 9727-188 — Will determine classification; directs Force Account tracking
2025-12-11 WSDOT SL 9727-217 — Vault does not qualify as Major Underground Utility
2025-12-23 Skanska LTR 303 — Requests reconsideration
2026-01-08 WSDOT SL 9727-235 — Reaffirms: not a Major Underground Utility or Service Line
2026-01-22 Skanska LTR 327 — Notice of Protest 013
2026-01-26 WSDOT SL 9727-250 — Acknowledges protest; supplement anticipated by February 9
2026-02-09 Skanska LTR 345 — Supplemental protest: KCM refused to direct; “property improvement” not defined in Contract
2026-02-18 KCM Vault Coordination Meeting — WSDOT, KCM, Skanska agree raise-to-grade is simplest; KCM later raises safety concerns
2026-03-02 WSDOT SL 9727-285 — Denies protest; cites GP 1-07.17(9).4, GP 1-07.16(1), RFP 2.16.3.5.6
2026-03-13 AECOM Notice of Dispute — Formal dispute per Section 1-04.5(1); intends DRB referral
2026-03-16 Skanska LTR 378 — Response to SL-285 + 3 resolution proposals + AECOM Dispute Notice (attached). Last day of 14-day dispute window.

5. Cost & Time

Skanska’s Claim

CategoryAmount
Claim AmountNot quantified (Force Account tracking per SL 9727-188)
Schedule ImpactNot quantified
Total Cost ClaimedTBD
Schedule ExtensionTBD

Skanska’s Proposed Resolution Paths

PathMechanismDescription
1Section 1-09.6Convert existing Force Account work to agreed lump sum. WSDOT directed FA tracking in SL-188.
2Section 1-04.4(1)Change order for vault work as added scope from undisclosed site condition.
3Section 1-07.17(10)WSDOT determines KCM vault is WSDOT cost responsibility, processed as directed change.

WSDOT Exposure Scenarios

ScenarioCostTime
WSDOT position (full denial)$0None
Resolution via FA conversion or COFA amount (TBD)TBD
DRB hearing (worst case)FA amount + markupTBD