INTERNAL MEMO — DO NOT SEND
Date: 2026-03-12
Prepared by: WSDOT Claims Analysis
Subject: Protest 014 — NB405 Bridge 405/103E Widening / ATC-1 Interpretation — Internal Analysis and DRB Preparation
Responding to: Skanska LTR 356 (Feb 20, 2026) — Notice of Protest 014; Skanska LTR 370 (Mar 6, 2026) — GP 1-04.5(2) Supplemental
Determination deadline: ~March 27, 2026 (21 calendar days after supplemental receipt per GP 1-04.5)
Finding Summary: The protest is without merit. ATC-1 was approved unconditionally and is incorporated into the contract through the DB’s Proposal. ATC-1 text (Items 3, 4, 6) and Figure 2 establish structural continuity. The DB is not entitled to adjustments.
| Section | Title | Key Language |
|---|---|---|
| RFP 2.13.1 | Bridge Widenings | 405/103E listed, TR level 5. |
| RFP 2.13.4.1.2 | Foundation Requirements | Drilled shafts (ATC-1 modified). |
| RFP 2.13.4.1.2 | Widening Design Criteria | “continuous beam across pier” (NOT removed by ATC-1). |
| ATC-1 Page 1 | Pier Walls | “act as extended shear wall for the new widening.” |
| ATC-1 Item 3 | Combining Footings | “spread footings will be combined”; “final design of combining…determined during final design.” |
| ATC-1 Item 4 | Pier Wall per Figure 2 | Pier wall configuration per Figure 2. |
| ATC-1 Item 6 | Match Existing Structure | “widened to match the existing structure.” |
| ATC-1 Figure 2 (C-227) | Combined Spread Footing | COMBINED SPREAD FOOTING, continuous widening depicted. |
| GP 1-01 | ATC Definition | Approved Technical Concept definition. |
| GP 1-03.2 | Order of Precedence + Clause 3 | Order of precedence; Clause 3 binds DB to proposal commitments. |
| GP 1-03.7 | “Approved” Defined | “approved” = conformance to contract. |
| GP 1-04.4(5)(n) | ATC Implementation Costs | ATC implementation costs = DB exclusive responsibility. |
| GP 1-04.5 | Protest Procedure | Protest procedure and timelines. |
ATC-1 was approved unconditionally during the procurement phase and is incorporated into the contract through the DB’s Proposal. Per GP 1-03.2, the DB’s Proposal (including all approved ATCs) forms part of the contract documents. ATC-1’s text and figures are binding contract requirements, not merely suggestions or design guidance.
When ATC-1 Items 3, 4, and 6 are read together with Figure 2 and the unmodified RFP 2.13.4.1.2 continuity requirement, a single coherent picture emerges: the widening must be structurally continuous with the existing bridge. The DB’s attempt to parse individual items in isolation ignores the contract’s integrated structure. Figure 2 (C-227) depicts a COMBINED SPREAD FOOTING with continuous widening — this is the graphic expression of the textual requirements.
WSDOT corrected the “Forward Compatibility” terminology in SL 9727-237 but expressly reaffirmed the underlying structural continuity requirement. The label was imprecise; the requirement (Items 3, 4, 6) stands independently of whatever terminology is used to describe it.
Correspondence Sequence:
The correction of a label does not withdraw the substance. Items 3, 4, 6, and Figure 2 exist independently of whatever name WSDOT or Skanska attach to the concept. Skanska’s argument conflates terminology correction with substantive withdrawal.
This is the core of the dispute. Each ATC-1 element independently supports structural continuity:
ATC-8 Consistency Rebuttal: The DB may argue that ATC-8 demonstrates a different approach. ATC-8 addresses a different bridge with different conditions and different contract provisions. Different bridges have different contracts — this comparison is irrelevant.
GP 1-03.2 Clause 3 establishes that where the DB’s Proposal offers higher quality, additional services, or terms more advantageous to WSDOT, those commitments are binding. The clause operates in one direction only — it elevates the DB’s commitments but never reduces contract requirements.
Continuous widening per ATC-1 qualifies under all three categories:
GP 1-04.4(5)(n) states that ATC implementation costs are the DB’s exclusive responsibility. This provision is absolute — it does not contain exceptions for cost increases, unforeseen difficulties, or changed interpretations. Regardless of the outcome of the structural continuity question, the DB bears the cost of implementing ATC-1 as written.
HIGHEST PRIORITY — New argument requiring detailed rebuttal.
Terry Bondy (sheet BF06) asked why the closure pour was NOT shown — a comment that questions an omission. AECOM mischaracterizes this as a neutral inquiry. Eight-point rebuttal:
The reliance/estoppel argument fails on multiple grounds:
The DB argues that changed geotechnical conditions justify deviating from ATC-1’s structural continuity requirement. This argument fails because:
The DB cites a Sonia Berriz statement to suggest internal WSDOT disagreement. This argument actually supports WSDOT:
| DB Assertion (LTR 356) | WSDOT Rebuttal |
|---|---|
| ATC-1 does not require structural continuity between widening and existing structure. | Items 3, 4, 6, and Figure 2 independently and collectively establish structural continuity. See Pillar 2. |
| WSDOT withdrew the “Forward Compatibility” requirement in SL 237. | SL 237 corrected terminology but expressly reaffirmed the substantive requirement. See Pillar 1. |
| Comment #9 closure constitutes acceptance of the DB’s design approach. | Comment closure does not override contract provisions. GP 1-03.7 defines “approved.” See Pillar 5. |
| The DB reasonably relied on WSDOT’s apparent acceptance. | Reliance fails. Contract text was available throughout. RFI 461 undermines reliance. See Pillar 6. |
| Changed geotechnical conditions justify deviation from ATC-1. | ATC-1 obligation is unconditional. Proper path is DBIC. See Pillar 7. |
| BDM and industry practice support the DB’s approach. | External standards do not override specific contract text. See Pillar 8. |
| DB Assertion (LTR 370) | WSDOT Rebuttal |
|---|---|
| AECOM analysis of comment #9 history shows WSDOT accepted non-continuous design. | Comment questions an omission, not endorses it. AECOM’s language escalates within its own document. See Pillar 5. |
| Sonia Berriz statement shows internal WSDOT disagreement. | Berriz statement actually supports WSDOT (“do not believe design meets contract requirements”). See Pillar 9. |
| ATC-8 demonstrates WSDOT accepts non-continuous approach for other bridges. | Different bridges have different contracts. ATC-8 addresses a different structure with different provisions. |
| Pat’s admission supports design flexibility. | Pat’s statement (“thought they would be ok”) is an informal comment that does not override written contract provisions or GP 1-03.7. |
| ID | Anticipated Argument | Pre-Emption |
|---|---|---|
| CA-1 | WSDOT is changing its position after years of apparent acceptance. | WSDOT identified a nonconformance and directed compliance. Standard contract administration. Consistent direction since March 2025. |
| CA-2 | The cost of structural continuity exceeds the DB’s bid assumptions. | GP 1-04.4(5)(n): ATC implementation costs are DB’s exclusive responsibility regardless of magnitude. |
| CA-3 | Structural continuity is not feasible given site conditions. | WSDOT offered DBIC path for infill shear walls. Feasibility challenges require DBIC, not unilateral deviation. |
| CA-4 | The contract is ambiguous regarding continuity. | Items 3, 4, 6, Figure 2, and RFP 2.13.4.1.2 are unambiguous. Read-together analysis yields a single coherent interpretation. |
Rebuts any claim that WSDOT has not provided sufficient direction.
| Date | Document | Direction Given |
|---|---|---|
| 2025-08-19 | WSDOT SL 9727-201 | Initial direction identifying ATC-1 structural continuity requirement for 405/103E widening. Established WSDOT’s position that the DB’s design must conform to ATC-1 commitments. |
| 2025-11-18 | WSDOT SL 9727-237 | Corrected “Forward Compatibility” terminology. Expressly reaffirmed the structural continuity requirement based on ATC-1 Items 3, 4, 6, and Figure 2. |
| 2026-02-10 | WSDOT SL 9727-262 | Responded to LTR 333. Reaffirmed WSDOT’s position. Reiterated that ATC-1 requires structural continuity and that DBIC is the proper vehicle for any proposed deviation. |
WSDOT has provided three written communications over six months, maintained a consistent position throughout, and offered to support a DBIC for alternative approaches to meeting the structural continuity requirement.
| Request | Disposition | Rationale |
|---|---|---|
| Recognition that ATC-1 does not require structural continuity | DENIED | ATC-1 Items 3, 4, 6, Figure 2, and RFP 2.13.4.1.2 establish structural continuity. Read-together analysis is unambiguous. |
| Additional compensation for structural continuity implementation | DENIED | GP 1-04.4(5)(n): ATC implementation costs are DB’s exclusive responsibility. |
| Contract Time adjustment | DENIED | GP 1-04.4(5)(m) and (n): ATC-related schedule impacts within DB risk allocation. |
| Withdrawal of WSDOT direction requiring continuity | DENIED | WSDOT direction is consistent with contract requirements. No basis for withdrawal. |
Option A — Deny after supplemental review. Issue determination denying Protest 014 on all grounds. Reaffirm SL 9727-262 and the structural continuity requirement. Cite dispute procedures per GP 1-04.5(1). The determination must address each pillar concisely, with emphasis on Pillar 5 (Comment #9) as the DB’s strongest new argument.
Option B — Proactive DRB preparation. Begin assembling the DRB position paper now. Structure around the nine pillars. Prepare witness outlines for Berriz, Sizivu, Bondy, and Pang. Compile the full comment #9 history with original records (not AECOM’s characterization). Prepare a read-together exhibit showing ATC-1 Items 3, 4, 6, and Figure 2 side by side.
Recommendation: Pursue both concurrently. The determination deadline (~March 27, 2026) requires prompt action on Option A, while DRB preparation should proceed in parallel given the near-certainty that the DB will escalate to dispute.
INTERNAL MEMO — Prepared 2026-03-12. Nine-pillar analysis covering ATC-1 structural continuity, Forward Compatibility correction, Comment #9 closure, reliance/estoppel, geotechnical conditions, BDM/industry practice, Berriz statement, GP 1-03.2 Clause 3, and GP 1-04.4(5)(n) risk allocation. DRB preparation recommended concurrent with determination.