Notice
Protest
Determination
Dispute
Hearing

1. Executive Summary

Decision Requested

Prepare for Disputes Review Board (DRB) referral on Protest 012. WSDOT’s position is that TR 2.18.4.6.3 explicitly requires bucket truck maintenance access for CCTV systems, and that the Design-Builder’s Camera Lowering Device (CLD) approach was a non-compliant design that the DB must correct at its own cost. WSDOT’s protest denial (SL 9727-225, SL 9727-261) was correct. The dispute awaits Skanska’s written Dispute Referral per RFP Section 1-04.5(1).18.

  • Recommendation: Deny all claims — protest is without merit
  • Cost Exposure: $104,879 claimed (AECOM $91,199 + Skanska $13,680)
  • Risk Level: Low-to-moderate — contract language is explicit; main vulnerability is DB’s collaborative-development equitable argument

Core Question

Did TR 2.18.4.6.3 require bucket truck maintenance access for the CCTV system at SB I-405 ~Sta. 4014+50, making the Design-Builder’s Camera Lowering Device approach a non-compliant design correctable at the DB’s cost — or did WSDOT’s rejection of the CLD approach during design review constitute a change to the Contract entitling the DB to an equitable adjustment?

The Contract (TR 2.18.4.6.3) explicitly requires that “Maintenance vehicle access shall allow bucket trucks to park adjacent to the CCTV structure.” The Design-Builder proposed a Camera Lowering Device instead of a bucket truck pullout, citing the NE 160th Street overcrossing as a physical constraint. WSDOT and the DB informally discussed the CLD approach during early design coordination. At RFC close-out in March 2025, WSDOT Maintenance rejected the CLD approach and required bucket truck access per TR 2.18.4.6.3.

After an 8-month design standstill, the parties agreed at a November 2025 Task Force meeting to expand the Comm Hub site to accommodate bucket truck access, requiring pole relocation. Skanska submitted a change order request via LTR 294 (December 9, 2025). WSDOT denied the change order via SL 9727-225 (December 24, 2025). Skanska protested via LTR 313 (January 7, 2026) and supplemented via LTR 330 (January 23, 2026) with a $104,879 claim. WSDOT denied the protest via SL 9727-261 (February 6, 2026). Skanska filed a Dispute Notification via LTR 354 (February 20, 2026); WSDOT acknowledged via SL 9727-278 (February 23, 2026).

Issue ID
ISS-012
Amount Claimed
$104,879
Time Impact
8-mo standstill (TBD)
Status
Deny

2. Skanska Assertions and WSDOT Position

A CLD Is a “Current Maintenance Method” Under TR 2.18.5.2 Strong

Skanska Assertion

TR 2.18.5.2 requires all ITS devices to be “accessible and maintainable using current maintenance methods and materials.” A Camera Lowering Device is a current maintenance method used by WSDOT when no other options are available. Therefore, the Contract permits either bucket truck or CLD access for CCTV maintenance, and WSDOT’s rejection of the CLD was a change, not enforcement of an existing requirement.

WSDOT Position

TR 2.18.4.6.3 is a CCTV-specific provision that explicitly requires “bucket trucks to park adjacent to the CCTV structure.” TR 2.18.5.2 is the general ITS maintenance provision. Under standard contract interpretation, the specific provision controls over the general. A bucket truck IS a current maintenance method — satisfying 2.18.4.6.3 also satisfies 2.18.5.2; the reverse is not true. The DB’s reading would render TR 2.18.4.6.3 surplusage: if any “current method” suffices under 2.18.5.2, there was no reason to specifically mandate bucket trucks in 2.18.4.6.3. Appendix T1 (NWR ITS Design Requirements, a Contract Document) further confirms bucket truck access for CCTV in two additional sections (T1 §1.12.2.1, T1 §2.3.2.3).

TR 2.18.4.6.3 · TR 2.18.5.2 · GP 1-03.2 · Appendix T1 §1.12.2.1, §2.3.2.3
B Appendix M1 Implied No Pullout Was Required Strong

Skanska Assertion

The RFP Appendix M1 conceptual plans showed the existing camera on the existing pole at ~Sta. 4014+50 to be replaced. No pullout was depicted in the conceptual plans, implying that no pullout was required and that a CLD approach was consistent with the intended design.

WSDOT Position

Appendix M1 is classified as a Reference Document (“BC” classification per Appendix A1). Per GP 1-03.1, “Reference Documents are for information purposes only and the Design-Builder shall rely upon Reference Documents at its own risk.” TR 2.18.4.6.3 is a Technical Requirement (higher priority per GP 1-03.2) and explicitly requires bucket truck access. A Reference Document showing the existing configuration does not override a Technical Requirement specifying the design standard.

GP 1-03.1 · GP 1-03.2 · Appendix A1 (M1 = “BC” Reference) · TR 2.18.4.6.3
C WSDOT Collaborated on CLD and Then Changed Its Position Moderate

Skanska Assertion

Per AECOM’s PCN-00100 (attached to LTR 294), the DB and WSDOT “collaborated during task force meetings and agreed on a solution” using a CLD, validated it in a field walk, and the CLD was “agreed upon in the TF meeting with WSDOT as the best possible solution.” WSDOT Maintenance then “changed their position” at RFC close-out in March 2025, refusing to close comments and requiring bucket truck access. This reversal constitutes a change.

WSDOT Position

Per GP 1-03.7, “oversight, spot checks, audits, reviews, tests, and inspections conducted by WSDOT do not constitute approval nor acceptance of the materials or Work inspected or reviewed or waiver of any Warranty.” Task Force discussions and field walks are part of the iterative design review process, not formal approvals. Only a Change Order modifies contract requirements. No Change Order was ever issued approving the CLD approach. WSDOT Maintenance’s March 2025 RFC comment enforced TR 2.18.4.6.3 — a requirement that existed from contract execution. WSDOT did not “change its position”; what changed was the DB’s awareness that its CLD design didn’t meet the contract. The DB’s own SOW acknowledges “WSDOT has seen the concept of a bucket truck access… and indicated that the design-build team should advance this concept.”

GP 1-03.7 · GP 1-03.9 (Waiver) · TR 2.18.4.6.3 · GP 1-04.4(5)(b)
D WSDOT’s RCSR Rejection Was a Preferential Engineering Decision, Not a Contract Requirement Strong

Skanska Assertion

WSDOT Maintenance preferred bucket truck access, but the Contract did not require it — the RCSR comment was a preferential engineering decision that effectively imposed new requirements on the DB.

WSDOT Position

TR 2.18.4.6.3 explicitly requires “bucket trucks to park adjacent to the CCTV structure.” This is not a preference — it uses the mandatory “shall.” WSDOT Maintenance’s RCSR comment identified a non-compliant design during design review. Per GP 1-04.4(5)(b), design changes required during WSDOT’s review “for consistency with the requirements of the Contract Documents” are the DB’s exclusive responsibility and are not eligible for change orders. There was no discretionary preference involved — the RCSR comment aligned precisely with the contract language.

TR 2.18.4.6.3 · GP 1-04.4(5)(b) · GP 1-03.7
E NE 160th Overcrossing Physical Constraint = Additional Scope Strong

Skanska Assertion

The NE 160th Street overcrossing creates a physical constraint that makes a standard Type 2 maintenance pullout impossible at the existing CCTV pole location, requiring pole relocation. This site condition creates additional scope not contemplated in the original design.

WSDOT Position

The DB accepted the Contract including TR 2.18.4.6.3 and the existing site conditions at the time of proposal. Per GP 1-04.1, “the Contract Price includes the cost of performing each portion of the Work needed to meet Contract requirements.” The NE 160th overcrossing was a known site condition. If bucket truck access required pole relocation given the constraint, that design solution is the DB’s responsibility. The constraint is not a WSDOT-directed change; it is a site condition the DB was required to design around to meet TR 2.18.4.6.3.

GP 1-04.1 · GP 1-04.4(5) · TR 2.18.4.6.3

3. Risk

Strengths

  • TR 2.18.4.6.3 is explicit and unambiguous: “bucket trucks” is specifically named, uses “shall,” and is CCTV-specific — cannot be overridden by general “current maintenance methods” language in TR 2.18.5.2
  • Appendix T1 §1.12.2.1 and §2.3.2.3 independently confirm bucket truck requirement for CCTV — the word “bucket truck” appears in three separate contract locations
  • GP 1-03.7 negates reliance on TF discussions and field walks as formal approvals
  • GP 1-04.4(5)(b) expressly excludes design review corrections from change order eligibility
  • The DB’s own PCN-00100 acknowledges bucket truck as the correct endpoint solution
  • Parallel provision TR 2.18.4.7.1 (VMS) uses identical language — confirms intentional, consistent specificity
  • DB never submitted a DBIC despite being aware the CLD approach was in question

Potential Weaknesses

  • Equitable reliance: 8-month design standstill (March–November 2025) occurred while parties explored alternatives; DRBs may be sympathetic to delay cost arguments even if legal position is clear
  • AECOM’s narrative (PCN-00100) characterizes early discussions as a “collaborative agreement” — emotionally compelling even if legally insufficient
  • Physical impossibility of CLD at original location was genuine and visible; DRBs may view the standstill as at least partly attributable to WSDOT’s delayed formal enforcement
  • Schedule analysis incomplete in LTR 330 (GP 1-04.5(2)(d)); if DB provides full CPM analysis in Dispute Referral, schedule entitlement could re-emerge

Fatal Flaw in DB’s Position

The DB’s reading of the Contract renders TR 2.18.4.6.3 meaningless. If TR 2.18.5.2 permits any “current method” including CLD, then the explicit “bucket trucks” language in TR 2.18.4.6.3 has no operative effect. This is a textbook surplusage argument: contract provisions must be interpreted to give effect to all terms, not to render provisions superfluous.

Defense Layering

LayerDefenseUse In
1. TR 2.18.4.6.3 is explicit: “bucket trucks” + “shall” + CCTV-specific. Specific controls over general (TR 2.18.5.2). Three independent contract references (TR, T1 §1.12.2.1, T1 §2.3.2.3). DB’s reading renders TR 2.18.4.6.3 surplusage. DRB Referral / Primary
2. GP 1-04.4(5)(b): Design review corrections are not change orders. WSDOT identified a non-compliant design; DB must correct at its own cost. No OIC was issued. DRB Referral / Secondary
3. GP 1-03.7: TF discussions and field walks are not formal approvals. No Change Order approved the CLD. DB cannot claim equitable reliance on informal review interactions. DRB Hearing / Anti-reliance
4. Appendix M1 is a Reference Document (GP 1-03.1). It shows existing conditions for reference only and cannot override TR 2.18.4.6.3. DRB Hearing / Document classification

Fallback Position

If DRB finds some equitable credit is warranted for the 8-month standstill, WSDOT should argue that (a) the delay was caused by the DB’s own non-compliant design approach, not WSDOT’s enforcement, and (b) any credit should be limited to incremental costs during the standstill period only — not the full redesign cost ($104,879). The redesign itself is clearly the DB’s responsibility under GP 1-04.4(5)(b).

4. Chronology

WSDOT
Skanska
Milestone
Oct 2022 – Mar 2026 Full timeline →
Date Event
2022-10-25 RFP issued — TR 2.18.4.6.3 requires bucket truck access for CCTV maintenance. Appendix M1 (Reference Document) shows existing camera on existing pole near NE 160th St.
2023-07-01 Contract No. 009727 executed — All TR Chapter 2 requirements binding on Design-Builder
~2024-2025 Early design coordination — DB and WSDOT discuss CLD approach at Task Force meetings. Field walk conducted. AECOM characterizes outcome as “agreed” solution.
2025-03-13 WSDOT Maintenance rejects CLD at RFC close-out — requires bucket truck access per TR 2.18.4.6.3. Area grayed out in RFC submission. 8-month design standstill begins.
2025-11-05 Task Force meeting — Parties agree to expand Comm Hub site; CCTV pole relocation required for bucket truck access
2025-12-09 Skanska LTR 294 — Formal change order request; AECOM PCN-00100 attached. Claims “agreed-to solution with WSDOT.”
2025-12-24 WSDOT SL 9727-225 — Written Determination denying change order; cites TR 2.18.4.6.3, Appendix T1 §1.12.2.1, §2.3.2.3
2026-01-07 Skanska LTR 313 — Notice of Protest 012; requests 75-day extension. Timely (14 days from SL 225).
2026-01-08 WSDOT SL 9727-236 — Acknowledges protest; denies 75-day extension; grants 1 day for MLK; supplemental deadline January 23
2026-01-23 Skanska LTR 330 — Supplemental; $104,879 claim (AECOM $91,199 + Skanska $13,680); schedule “TBD”
2026-02-06 WSDOT SL 9727-261 — Protest denied; bucket truck access road required per TR 2.18.4.6.3; CLD not acceptable under Appendix B07
2026-02-20 Skanska LTR 354 — Dispute Notification per RFP Section 1-04.5(1); claims CLD was collaboratively developed; asserts bucket truck requirement is a change. Timely (14 days from SL 261).
2026-02-23 WSDOT SL 9727-278 — Acknowledges dispute; awaiting written Dispute Referral
2026-02-23 Dispute filed. Position Paper outline created. Awaiting written Dispute Referral from Skanska.

5. Cost & Time

Cost Breakdown (from LTR 330)

ComponentHoursAmount
General/Management (AECOM)48 hrs$18,945
Roadway (AECOM)120 hrs$28,829
Roadside Restoration (AECOM)40 hrs$10,022
ITS (AECOM)118 hrs$27,944
Design QM (AECOM)21 hrs$5,460
AECOM Subtotal (347 hrs + 15% markup)347 hrs$91,199
Skanska direct costs$13,680
Total $104,878.85
Schedule ExtensionTBD — actual delay analysis pending

WSDOT Exposure Scenarios

ScenarioCostTime
WSDOT position — deny all claims$0None
DRB partial — standstill delay credit only (not redesign)$20K–$50K (est.)Possible partial
Worst case — DRB finds OIC + schedule entitlement$104,879TBD (up to 8 months)

Relief Requests and Disposition

#Relief RequestedWSDOT Disposition
1 Change order for $104,879 in redesign costs Denied — TR 2.18.4.6.3 is existing requirement; GP 1-04.4(5)(b): design review corrections not eligible for change order
2 Recognition that CLD rejection was an OIC Denied — No OIC issued; WSDOT enforced existing contract requirement during design review
3 Schedule entitlement for 8-month standstill (reserved — analysis TBD) Denied (preliminary) — Standstill caused by DB’s non-compliant CLD design; no WSDOT-directed delay. GP 1-04.5(2)(d) schedule analysis not provided.