Notice
Protest
Determination
Dispute
Hearing

1. Executive Summary

Decision Requested

Approve sending DRB Referral Letter to initiate formal Dispute Review Board proceedings.

  • Recommendation: Proceed to DRB on one question
  • Cost Exposure: $450K–$7.8M (two countermeasure options); excludes CLOMR, permitting, reconstruction
  • Risk Level: Low-to-moderate — strong contract language, but two bridges already constructed

DRB Question

Does Section 2.30.5.2.1 require the Design-Builder to apply the “not low” lateral migration determination to Sammamish River structures, or does it permit the Design-Builder to reach a different determination through independent analysis?

Section 2.30.5.2.1 provides: “The Sammamish River ‘not low’ lateral migration determination discussed in the Sammamish River Migration Risk Assessment (Appendix H) shall apply to the new structures within the river flow limits defined by the 500-year flood elevation.”

“Shall apply” mandates the “not low” determination as a contract requirement. H26 concludes: “The risk of channel migration… is NOT LOW and therefore will require further analysis during final design.” The word “therefore” shows further analysis is a consequence of the NOT LOW determination, not a license to revisit it.

Three bridges are affected: the Ramp Bridge (constructed), Mainline Bridge (in construction), and DAR Bridge (design phase, April 2026 construction). Skanska’s supplemental (LTR 322) presents two countermeasure cost scenarios: Option 1 ($7,809,741) — vertical steel sheet pile walls; Option 2 ($450,032) — rock and log vanes per HEC-23. Both exclude CLOMR, extended general conditions, permitting, and reconstruction.

Skanska/AECOM’s Table 2.30-B argument—that the Sammamish bridges are “fish passage structures” subject to a “low” standard—fails because Table 2.30-B identifies specific fish passage structures by name and does not include the I-405 bridges. Two key submittals are directly affected: the Draft FHD (CRE-00888, rejected January 2025) and the Zero Rise Report (CRE-01059, blocked). Between August 2024 and January 2025, WSDOT and Skanska/AECOM engaged in 8+ documented OTS review interactions without reaching agreement on the classification.

Per Section 1-03.5, the IED interprets existing requirements and creates no entitlement to cost or time adjustment. The Design-Builder had six months’ notice before contract award. H26 was added via Addendum 9 (Jan 2023); Section 2.30.5.2.1 via Addendum 14 (Mar 2023). Section 2.14.6.11 zero-rise certification is blocked pending resolution.

2. Skanska/AECOM Assertions and WSDOT Position

1 Addendum Sequencing Strong

Skanska/AECOM Argument

H26 added first as “reference only.” “Shall apply” added later. Suggests no fixed intent.

WSDOT Rebuttal

Contract signed as a whole. Addendum 14 added the “shall apply” language after Addendum 9 added H26. The sequence shows WSDOT refined the requirement to be more explicit, not less.

2 “Further Analysis” Language Strong

Skanska/AECOM Argument

H26 says determination “will require further analysis during final design.” Therefore analysis can refine or override.

WSDOT Rebuttal

H26 reads: “The risk of channel migration… is NOT LOW and therefore will require further analysis.” The word “therefore” shows further analysis is a consequence of the NOT LOW determination, not a license to revisit it. DB’s reading renders Section 2.30.5.2.1 meaningless.

3 Contract Harmonization Strong

Skanska/AECOM Argument

Contract must be read as integrated whole, including FHD analysis requirements.

WSDOT Rebuttal

Specific governs general. The explicit “shall apply” in Section 2.30.5.2.1 is a specific mandate that controls over general FHD analysis requirements.

4 Hydraulics Manual Version Strong

Skanska/AECOM Argument

Contract-incorporated March 2022 manual lacked lateral migration methodology.

WSDOT Rebuttal

Section 2.30.5.2.1 is self-contained. It does not depend on the Hydraulics Manual to establish the “not low” requirement. The manual provides methodology for compliance. The requirement derives from Section 2.30.5.2.1.

5 Technical Merit (BSTEM, HEC-20, FHWA) Strong

Skanska/AECOM Argument

BSTEM, HEC-20, FHWA Rapid Assessment demonstrate risk is actually “low.”

WSDOT Rebuttal

Engineering analysis cannot override explicit contract language, regardless of quality. Section 2.30.5.2.1 says “discussed in” (citing a completed assessment) + “shall apply” (mandating its result). The proper mechanism to change the classification is a DBIC under Section 1-04.4(2). No such request has been submitted.

6 H26 as Contract Document (Section 1-03.1) Strong

Skanska/AECOM Argument

H26 is “called out as a mandatory requirement” in Section 2.30.5.2.1, elevating it from Reference to Contract Document under Section 1-03.1.

WSDOT Rebuttal

Even if elevated, H26 says “NOT LOW,” which supports WSDOT’s position, not Skanska’s. Section 2.30.5.2.1 is the requirement source, not H26. The mandate is self-executing.

Strategy note: Do not raise this argument at the DRB. Keep rebuttal in reserve. If Skanska raises it, respond that H26’s own conclusion supports WSDOT.

7 No Direction Provided Strong

Skanska/AECOM Argument

WSDOT has not provided sufficient information to assess a path forward.

WSDOT Rebuttal

Direction given through SL 116 (IED, June 2025), workshop (Aug 2025), SL 139, SL 178 (CLOMR guidance), SL 220 (follow-up). Multiple compliance paths identified (structural or countermeasures per HEC-23).

8 WSDOT Causing Delay (DAR Bridge) Strong

Skanska/AECOM Argument

WSDOT’s position is delaying dependent design activities, especially DAR Bridge (April 2026).

WSDOT Rebuttal

DB has had since contract award (July 2023). IED issued June 2025. 8+ months have elapsed. Schedule risk results from proceeding with non-compliant design. Per Section 1-03.5, IED creates no schedule entitlement.

9 Table 2.30-B (“Fish Passage”) Strong

Skanska/AECOM Argument

Table 2.30-B classifies the Sammamish River bridges as “fish passage structures” subject to a “low” lateral migration standard.

WSDOT Rebuttal

Table 2.30-B identifies specific fish passage structures by name (e.g., Kelsey Creek, Swamp Creek culverts) and does not include the I-405 Sammamish River bridges, which are transportation structures spanning the river. Section 2.30.5.2.1 is a site-specific provision that expressly identifies the Sammamish River structures and mandates the “not low” determination, superseding any general table classification.

Section 2.30.5.2.1 · Table 2.30-B

3. WSDOT Position & DRB Considerations

Defense Layers

#Defense LayerAuthorityStrength
1“Shall apply” is dispositiveSection 2.30.5.2.1Strong
2IED authority, no entitlementSection 1-03.5Strong
3Pre-award notice (Form A, 6 months)Addendum 9, 14Strong
4Silent deviation — no DBIC filedSection 1-04.4(2)Strong
5LTR 322 deficienciesSection 1-04.5Moderate
6WSDOT demonstrated good faithPartnering recordFavorable
7H26 rebuttal — even under 1-03.1, H26 says “NOT LOW”H26Reserve

DRB Considerations

  • Two bridges already constructed. Sympathy factor, but the contractual question is unchanged regardless of construction status.
  • DAR Bridge may already comply. AECOM’s draft analysis suggests current shaft design accommodates “not low” scour — Skanska may call the dispute “academic.” WSDOT response: low-cost compliance makes the silent deviation less defensible.
  • DAR Bridge schedule pressure. Design blocked pending resolution (April 2026). WSDOT response: requirement has been in the Contract since award; WSDOT first flagged Aug 2024.
  • CLOMR is conditional. 12–18 month timeline applies only if BFE rises. Countermeasure approaches may avoid a BFE rise entirely.
  • Sophisticated Skanska/AECOM position. Multiple legal theories (addendum sequencing, harmonization, 1-03.1 reclassification, Table 2.30-B) require careful, layered rebuttal.
  • Section 1-03.1 argument. Double-edged sword — even under Skanska’s own reading, H26 says “NOT LOW.” Keep rebuttal in reserve.
  • Collaborative resolution possible. DAR Bridge negotiation could narrow the dispute scope.
  • DRB may lean toward compromise. Cost disparity ($450K vs. $7.8M) may reinforce tendency toward practical resolution.
  • Cost disparity ($450K vs. $7.8M). Wide range suggests LTR 322 cost analysis is preliminary and may not reflect the most efficient compliant solution.

Fallback Position

If DRB recommends compromise: accept countermeasures for DAR Bridge only if it preserves the “shall apply” framework as precedent. Resist any recommendation that the Design-Builder may override contractual design classifications through independent analysis — this precedent affects all IEDs on this project.

4. Chronology

WSDOT
Skanska
AECOM
Both
Key Events & Milestones Full timeline →
DatePartyEventDocument
2023-01-26WSDOTAddendum 9 issued — adds Appendix H26Add. 9
2023-03-02WSDOTAddendum 14 issued — “shall apply” languageAdd. 14
2023-05-30SkanskaProposal submitted. Form A certifies all addendaForm A
2023-07-27WSDOTContract awarded
2023-08-10BothContract executed
2024-07-16AECOMDraft FHD submitted with “low” lateral migration (CRE-00888)CRE-00888
2024-08-06WSDOTReview comments flag “not low” issue (RCSR #3, #4)RCSR
2024-08-20SkanskaZero Rise Report submitted (CRE-01059). BlockedCRE-01059
2024-09-10BothFish Passage Task Force presentation
2024-09-30WSDOTAssink email: “low” only with non-erodible materials
2024-10-25SkanskaOTS revised FHD transmitted
2024-11-26BothLateral migration meeting, no resolution
2024-12-23SkanskaRevised FHD via email with BSTEM modeling
2025-01-10WSDOTTechnical comments on Dec 23 FHD
2025-01-13WSDOTFHD rejected. Review comments not resolved
2025-01-21WSDOTAdditional comments (Ng, Black, Sofield)
2025-02-10BothMulti-party technical meeting
2025-03-04AECOMRevised FHD submitted. Conclusion unchanged
2025-04-21WSDOTFirst written notice: does not concur with “low”Email
2025-06-13WSDOTIED issued — directs “not low”SL 116
2025-06-27SkanskaResponse to IED. Disputes interpretationLTR 204
2025-07-09WSDOTRE: LTR 204SL 125
2025-07-17SkanskaRequests workshopLTR 214
2025-07-21WSDOTAgrees to workshopSL 127
2025-07-23SkanskaPre-workshop AECOM position letterLTR 215
2025-08-07BothWorkshop held — no resolutionNotes
2025-08-15WSDOTWithholds determination while DB explores alternativesSL 139
2025-10-13WSDOTCLOMR guidance — 12–18 month warningSL 178
2025-12-17WSDOTFollow-up — no compliant solution presentedSL 220
2025-12-30SkanskaNotice of Protest — PCO 126LTR 309
2025-12-31WSDOTDenies 75-day request. Supplemental due Jan 16SL 228
2026-01-16SkanskaSupplemental — 138 pages, $450K–$7.8MLTR 322
2026-01-29WSDOTWritten Determination — denied “without merit”SL 252
2026-02-10AECOMDRAFT pier scour analysis for DAR BridgeDraft
2026-02-11AECOMNotice of Dispute — introduces Section 1-03.1 argument
2026-02-12SkanskaNotice of Dispute — formal DRB escalationLTR 348
2026-02-17AECOMDRAFT drilled shaft evaluation — DAR accommodates scourDraft
2026-02-20WSDOTAcknowledges dispute — awaits DRB referralSL 269

5. Cost & Time

Skanska’s Cost Estimates (LTR 322)

ScenarioCostSchedule RiskNotes
Option 1: Sheet Pile Walls$7,809,741Unknown352 fifty-foot steel sheets ($2.0M) + pile driving ($2.6M) + 20% markup ($1.3M). Excludes CLOMR, extended GCs, permitting, reconstruction
Option 2: Rock/Log Vanes (HEC-23)$450,032UnknownDesign ($127K) + FHD update ($106K) + construction. Bioengineering approach. Excludes CLOMR, extended GCs, permitting
DAR Bridge RFCApril 2026 at riskDesign blocked pending dispute resolution. 6+ months potential delay

Key Considerations

  • Interior pier prohibition: BDM Section 7.1.7.B states countermeasures “shall not be placed at interior piers.” The only compliant path is foundation design accommodating full scour depth.
  • AECOM draft analysis (Feb 2026): DAR Bridge shafts (100–135 ft) already accommodate “not low” scour — oversized for landslide demands. Only Piers 3 and 4 within 500-year flood limits. Ramp Bridge and Mainline Bridge not analyzed. Draft in WSDOT review.
  • Zero-rise certification: CRE-01059 submitted August 2024 but blocked per Section 2.14.6.11. Lateral migration classification affects scour countermeasure design, which affects the hydraulic model and BFE analysis.
  • CLOMR timeline: 12–18 months per SL 178, but conditional — only applies if BFE rises. Countermeasure approaches may avoid BFE rise entirely.